What Is the Lead Time for 500 Custom Team Bags in Season?

The number a club wants is a single figure. The number that matters is a date on a calendar, because bulk production is 35-50 days from written sample approval and the window closes early around Spring Festival. This piece builds the calendar backwards from a fixture and names the four points at which a club has to decide.

A club calendar marked with the tech pack sign-off, sample approval and bulk window
The bulk clock starts at written sample approval, not at the enquiry.
Quick answer

Work backwards from the date the kit has to be in a player's hands. Take bulk production as 35-50 days from written sample approval, sampling as 6-10 working days before that, and add freight on top. Then check the result against the Spring Festival window, because a calendar that crosses it does not shorten — it moves to the other side of it.

What Does Lead Time Actually Cover?

It covers three things that are usually quoted as one, and separating them is the whole trick. The first is sampling: 6-10 working days from a signed-off tech pack, extending to 12-15 working days where a new colour has to be matched or a new panel has to be developed. The second is bulk: 35-50 days from written sample approval. The third is freight, which is not production time at all and is quoted separately.

A club that hears "six weeks" and plans on six weeks has usually been quoted the bulk figure alone. A club that asks which two of the three that covers gets an answer it can put on a calendar. The distinction matters most in season, because in season the club is not planning a purchase — it is planning around fixtures that are already fixed.

Three stages, three triggers. Only one of them starts when the club sends an enquiry.
StageWhat starts itDurationWhat ends it
SamplingA signed-off tech pack6-10 working days (12-15 if a colour is new)A written sample approval
Bulk productionWritten sample approval35-50 daysA finished lot, packed
InspectionA finished lotWithin the bulk window, at AQL 2.5A release note
FreightA released lot, FOB XiamenVaries with the lane and the seasonArrival at the club

When Does the Clock Start?

Not at the enquiry, and not at the deposit. Bulk production starts at written sample approval, and sampling starts at a signed-off tech pack. Those are two different documents, and the gap between them is where most of the slippage in a club calendar actually happens.

A tech pack is signed off when the club has named the fabric, the compartments, the dimensions, the colour references and the decoration. A sample is approved when the club has seen the physical bag and said so in writing. Between the two sits a round of physical development, and the round can be repeated. The first order of a programme usually takes one round; a programme with an unresolved crest or an unmatched colour can take two or three.

How Do You Build the Calendar Backwards From a Fixture Date?

Start with the date the bag has to be in a player's hands, then subtract in order. Freight first, because it is the item a club most often forgets. Bulk second, taking the top of the range rather than the bottom until the tech pack is settled. Inspection third, which sits inside the bulk window rather than after it. Sampling fourth. And then, because everything above assumes a clear run, check what the result sits against.

The arithmetic for a 500-piece first order with a new club colour runs as follows: 12-15 working days of sampling, then 35-50 days of bulk, then freight. Call it three weeks of sampling, seven weeks of bulk and two to five weeks on the water, and a club is looking at roughly twelve to fifteen weeks from a signed-off tech pack to a bag in hand. A repeat order with the colour already matched takes the sampling figure down to 6-10 working days and removes a week and a half.

  • Fix the fixture date first, and write it down before any other figure.
  • Subtract freight, using the lane the club actually uses.
  • Subtract 50 days, not 35, until the tech pack is stable.
  • Subtract the sampling window, at 12-15 working days if any colour is new.
  • Subtract two weeks for the club's own decision time, which is never zero.
  • Read the resulting start date and ask whether it sits inside a shutdown.

What Is the Spring Festival Shutdown, and How Long Does It Really Last?

Spring Festival is the Lunar New Year, and it falls between late January and mid-February, moving every year. The public holiday itself is about a week. That is not the number a club should plan with.

The number a club should plan with is the effective closure, which is considerably longer. Production lines begin to wind down one to two weeks before the holiday, as workers travel home, and they do not run at full strength for one to two weeks after it, as workers return. A club planning against the public holiday alone will place an order that looks comfortable and lands inside a window in which nothing is being made.

There is a second effect that catches clubs out, and it runs before the shutdown rather than during it. The weeks immediately before Spring Festival are the busiest of the year for export bookings out of Fujian. Freight space tightens and sailings roll. A lot that was finished on time can still miss its vessel, and it is then held over the holiday rather than shipped.

The effective Spring Festival closure is four to six weeks, not one. Plan against the closure, not the holiday.
WindowWhat happensPlanning consequence
Two to three weeks before the holidayLines wind down; new jobs are not startedA tech pack signed off now is a February job, not a January one
The holiday week itselfProduction stopsNothing moves
One to two weeks after the holidayLines ramp back upOutput is below normal
Three to four weeks before the holidayExport bookings tightenBook the vessel before the lot is finished
The Spring Festival rule

If a club's calculated bulk window overlaps the shutdown in any way, the honest answer is not that the order will be late. It is that the order becomes a post-holiday job, and the club should plan the delivery date on the far side of the holiday and tell its squads so.

Which Other Shutdowns Hit a Team Bag Calendar?

Three more, none of them as severe. The National Day holiday in early October closes about a week and produces a smaller version of the same effect: a wind-down before, a ramp-up after, and tight bookings in the weeks preceding it. The Labour Day holiday at the start of May closes a few days.

The third is not a holiday at all. Late summer and early autumn is the peak export season for the northern hemisphere's own peak, and lines are at their fullest from roughly August to October. A 500-piece order booked in that window takes its place in a queue. It still runs inside 35-50 days, but the queue is the reason a club should book rather than hope.

Fujian also has a typhoon season, running roughly July to September, and a port closure of two or three days is a normal event in that window rather than an exceptional one. It is worth a line in the plan and not worth a contingency of its own.

What Happens If an Order Lands Just Before the Shutdown?

One of three things, and the club should know which before it commits. If the tech pack is signed off with enough of the sampling window left, the sample is made and approved before the wind-down, and bulk starts when the lines come back. That is the good outcome, and it costs the club the shutdown period and nothing else.

If the sample is made but not approved, the club holds a physical bag over the holiday and approves it on the far side. That is also a reasonable outcome, and it is the one a club should aim for when a decision is running late: get the sample into someone's hands before the holiday, even if the written approval follows.

The third outcome is the one to avoid. If the tech pack is signed off too late for sampling to finish, nothing physical exists over the holiday, and the whole sequence — sampling, approval, bulk — starts after it. The club loses the shutdown period and the sampling window both, and a delivery planned for March becomes one that lands in May.

How Does Freight Change the Answer?

Substantially, and more than most clubs allow for. Production is quoted FOB Xiamen, which means the lot is delivered to the vessel. What happens after that is the club's own arrangement, and the duration depends on the lane, the carrier and the season.

The seasonal part is the one that matters here. Freight into Europe and North America tightens in the run-up to both Spring Festival and the autumn peak, and a booking made late in those windows either costs more or rolls to a later sailing. A club working to a fixed fixture date should treat the booking as part of the calendar rather than as an afterthought that follows a finished lot.

Four freight factors. The first two move a date by weeks; the second two by days.
Lane factorEffect on the dateWhat to do
Pre-Spring Festival bookingsSpace tightens, sailings rollBook before the lot is finished
Autumn peak seasonLonger transit, fuller vesselsAdd a week to the plan
Typhoon season in FujianShort port closuresAdd two or three days, no more
Incoterm choiceChanges who books and who waitsSettle it before the enquiry, not after

One more item belongs in the freight line: the packing. Cartons are specified to survive the transit they are about to take, and ISTA publishes transit test procedures for packed products. A club that ships a season's kit once has less to worry about here than a club that ships monthly, but both should know the carton specification was considered rather than assumed.

The Incoterm decision is worth settling early, because it decides who carries the booking risk. FOB, CIF or DDP sets out what changes between them, and the landed cost tool turns the choice into a figure per unit.

Does 500 Pieces Take Longer Than a Smaller Quantity?

Not in production days. A 500-piece order sits inside the same 35-50 day bulk window as a much larger one, because the window is set by the fabric, the decoration and the line setup rather than by the piece count. MOQ 500 pcs per style and colourway is the floor at which a club colour and a club crest are worth setting a line up for; 300 pcs is open to discussion on a repeat, where the setup already exists.

What quantity does change is where the order sits in the queue, and therefore how early the club has to book. A programme running seven production lines at 200,000 pcs a month has real capacity, but capacity in a given week is finite. In the autumn peak, two clubs wanting the same week means one of them takes the following week. Booking early is what converts a delivery date from an estimate into a commitment.

A production line running club kit bags in a club colourway
Quantity does not change the production window; it changes where the order queues.

How Much Shorter Is a Repeat Order?

About a week and a half, and more than that in practice. Sampling on a repeat runs 6-10 working days rather than 12-15, because the colour is already matched, the pattern already exists and the decoration file is already made. There is no new reference set to agree.

More important than the saved days is the saved risk. A first order carries the risk that the colour comes back wrong, the crest comes back wrong, or both, and each of those means another sampling round. A repeat carries none of that, provided the reference set was retained. That is the practical argument for keeping coupons: it is not tidiness, it is what makes the second order predictable. The full argument is set out in Reorder consistency.

How Should a Multi-Squad Club Phase Its Deliveries?

A club with several age groups rarely needs every bag on the same day, and saying so at the enquiry is one of the most useful things it can do. Two deliveries a month apart spread the same total quantity across two windows, which takes pressure off the queue and gives the club a chance to correct anything the first delivery reveals.

The phasing has to be declared at the enquiry rather than negotiated later, because the production plan is built around it. A club that asks for 500 and then asks for 250 now and 250 later has changed the plan after it was made, and the second 250 will be treated as a repeat with its own window.

What Are the Four Ordering Points on a Club Calendar?

Every in-season programme has the same four, and they are worth writing into the club's own planning document rather than leaving to memory. The end-of-season review, at which the next season's quantity is estimated. The pre-season decision, at which the tech pack is signed off. The sample approval, which starts bulk. And the booking, which should be made before the lot is finished rather than after.

The four dates a club should write down

  • End-of-season review — estimate the quantity per squad and per colourway, and note which crews are new.
  • Pre-season decision — sign off the tech pack, with the colour reference and the crest file attached.
  • Sample approval — give it in writing, and date it, because bulk is counted from it.
  • Freight booking — make it before the lot is finished, and earlier than that in a pre-holiday window.
  • Delivery to squads — plan the issue date, not the arrival date; they differ by a week.
Four points, in order. Missing the second one is what pushes a programme across Spring Festival.
Ordering pointRoughly whenWhat it commits
End-of-season reviewWithin a month of the last fixtureAn estimated quantity
Pre-season decision12-15 weeks before the first fixtureThe tech pack
Sample approval7-8 weeks before the first fixtureThe bulk start date
Freight bookingBefore the lot is finishedThe vessel

Where Does Inspection Sit in the Calendar?

Inside the bulk window, not after it. Inspection at AQL 2.5 under ISO 2859-1, General Inspection Level II, is carried out on the finished lot before release, and the sample size and the accept and reject numbers come off the lot size. The sampling table gives both.

The reason to say this in a lead-time piece is that clubs sometimes plan inspection as a stage that follows production and adds to it. It does not, provided the criteria were agreed before the lot was made. Where it does add time is when a lot fails and has to be reworked, and the rework is the real schedule risk in a season with a fixed date. Clear criteria, agreed in writing before bulk, are what keep that risk small.

AQL 1.5 versus 2.5 sets out what changes between the two levels and what each one costs a club in rework probability.

How Do You Protect a Date When a Decision Runs Late?

Three moves, in order of how much they help. The first is to sign off the tech pack with the colour unspecified and match the colour during sampling, which keeps the sampling window open and removes the longest single item from the critical path. It costs a club one decision and saves the most time.

The second is to approve a sample conditionally — approving the construction and holding only the colour, so bulk can be booked against a construction that is settled. The third is to accept a split delivery and take the first squad's bags on the original date. All three are better than the default, which is to wait for everything to be settled before anything is booked.

What Should the Order Say About the Date?

It should say a date, and it should say what counts from what. Bulk counted from written sample approval, sampling counted from a signed-off tech pack, and delivery quoted FOB Xiamen on T/T 30/70. When those three appear on the order, a club can calculate its own calendar and check the supplier's arithmetic against it.

This is the whole basis on which we run programmes. We do not promise the fastest 20 days. We promise a delivery date you can calculate — one built out of named stages, each with a trigger, so a club can see where the time goes and what moves it. A date that cannot be calculated is not a commitment; it is a hope with a number attached.

The window itself, and what sets its two ends, is set out in Why 35 to 50 days.

A delivery schedule with the sampling window, bulk window and booking marked
A date you can calculate is built out of named stages, each with its own trigger.

What Is the Honest Answer?

For 500 custom team bags ordered in season, plan on twelve to fifteen weeks from a signed-off tech pack to bags in a player's hands, and plan on three months if the calendar touches Spring Festival. A repeat with the colour already matched takes about a week and a half off that, mostly out of sampling.

The single thing that moves the date most is not the quantity, the fabric or the decoration. It is how early the tech pack is signed off, because that is the one input a club controls entirely on its own side of the line.

Send the fixture date and we will work the calendar backwards

Tell us the date the bags have to be in a player's hands and the quantity per squad, and we come back with the four dates your programme has to hit.

Frequently Asked Questions

What is the lead time for 500 custom team bags?

Plan twelve to fifteen weeks from a signed-off tech pack to delivery: 6-10 working days of sampling (12-15 for a new colour), 35-50 days of bulk, then freight.

When does the production clock start?

At written sample approval. Sampling itself starts at a signed-off tech pack, which is a separate document.

How long is bulk production?

35-50 days from written sample approval, inspected at AQL 2.5 under ISO 2859-1.

How long does sampling take?

6-10 working days from a signed-off tech pack, extending to 12-15 working days where a new colour has to be matched.

How much time does Spring Festival add?

Treat it as a four to six week effective closure: a wind-down before the holiday, the holiday itself, and a ramp-up after it.

Which other shutdowns matter?

The National Day holiday in early October, the Labour Day holiday in May, and the August-to-October peak season, when lines are fullest.

Does a 500 piece order take longer than a larger one?

No. The 35-50 day window is set by the fabric and the decoration, not the piece count. Quantity affects where the order queues.

How much shorter is a repeat order?

About a week and a half out of sampling, and considerably less risk, because the colour and the decoration file already exist.

Should a club book freight before the lot is finished?

Yes, particularly in a pre-holiday window, when export bookings out of Fujian tighten and sailings roll.

When should a club sign off its tech pack?

Roughly twelve to fifteen weeks before the first fixture, and earlier than that if the calendar touches Spring Festival.

Can a club split the delivery across two dates?

Yes, and it helps — but it has to be declared at the enquiry, because the production plan is built around it.

What is the minimum order?

MOQ 500 pcs per style and colourway, with 300 pcs open to discussion on a repeat.

How is the finished lot inspected?

At AQL 2.5 under ISO 2859-1, General Inspection Level II, before release.

What are the payment and shipping terms?

T/T 30/70, FOB Xiamen; CIF and DDP available.

People Also Ask

How long do 500 custom team bags take?

Twelve to fifteen weeks from a signed-off tech pack to delivery.

When should a club order team bags for the new season?

Sign off the tech pack twelve to fifteen weeks before the first fixture.

How much time does Spring Festival add to an order?

Treat the effective closure as four to six weeks, not the one-week holiday.

Is a repeat order faster than a first order?

Yes — sampling drops from 12-15 working days to 6-10.

Does quantity change the production window?

No. The 35-50 day window is set by fabric and decoration, not piece count.

Sources and further reading

Every figure on this page is either our own programme data or attributed below. Open the originals before you write them into a specification.