Bag RFQ Template: 15 Fields Every Buyer Should Fill Out

A request for quotation is a form, not a message. Fifteen fields cover it: who is asking, what is being made, how many, in what material, to what standard, by when, where, on what terms, and what happens next. Each blank field is a guess the other side has to make.

Printed RFQ form with fifteen numbered fields on a clipboard
A form is completed; a message is interpreted.
Quick answer

A bag RFQ carries fifteen fields: buyer identity, style description, quantity per colourway, target price, drawings and pack status, material direction, hardware direction, artwork status, testing and compliance, sampling expectation, bulk window, destination and Incoterm, payment terms, inspection requirement and response deadline. Fill all fifteen and the price that comes back can be held to.

The reason an RFQ works as a form is that a quotation is arithmetic, and arithmetic needs inputs. Every field on the list below is an input to somebody else's calculation: quantity sets the material buy, the material direction sets the largest cost line, the destination sets the Incoterm and the documents, the testing list sets the laboratory spend. A field left out is not a neutral omission; it is an assumption made by the person doing the arithmetic.

That is why the same bag can come back at two different prices from two honest quotations. Neither side has been dishonest. One filled in a stock shell where the other assumed a coated one, and the difference is a material line rather than a margin.

Why Is an RFQ a Form Rather Than a Message?

Because a message has to be read and a form has to be completed. A buyer writing "please quote 500 cooler bags" has not said what the insulation is, what the liner is, whether the seams are welded, what the closure is, or where the bags are going. Every one of those is a question, and a question in a message becomes an email thread rather than a number.

There is a second reason that matters commercially. A form creates a record of what was asked, which is what makes the quotation defensible later. When the price moves — and it will, at some point — the RFQ is the document that says which of the fifteen inputs changed and which did not.

What Are the First Five Fields and Why Do They Come First?

Identity, description, quantity, target price and drawing status. The first four are trivial and the fifth is the one that decides everything else. A buyer who has a finished tech pack sends it with the RFQ and gets a real number. A buyer who has a sketch sends the sketch and gets an indication. A buyer who has neither sends a description and gets a range.

The target price field is the one buyers resist filling in, and it is the most useful one on the form. Stating a target does not weaken the buyer; it tells the other side which construction directions are worth costing. Without it, a quotation is built to a specification the buyer may not be able to sell at.

Fifteen fields. The five that most often get skipped are nine, twelve, fourteen, four and fifteen — in that order.
FieldWhat you writeWhy it is thereWhat a blank one produces
1. Buyer identityLegal entity, contact, marketSets who the quotation is issued toA quote addressed to nobody in particular
2. Style descriptionWhat the bag is and what it carriesSets the construction directionA bag built for the wrong duty
3. Quantity per colourwayPieces per colourway, and the totalSets the material buy and the price breakA price at the wrong volume tier
4. Target priceA target and the currencyTells the other side which directions to costA specification the buyer cannot sell at
5. Drawing and pack statusSketch, pack, or a physical referenceTells the other side how firm the number can beAn indication presented as a quotation
6. Material directionShell, lining and foam, with a second optionThe largest cost line in the bagA stock substitution nobody chose
7. Hardware directionSizes, finishes, performance figuresHardware is bought, not madeA part that fits and fails in use
8. Artwork statusFile, process, position, whether approvedPrint and embroidery are separate cost linesA decoration cost that arrives later
9. Testing and complianceNamed standards and documentsLaboratory spend and certificate costA claim nobody budgeted for
10. Sampling expectationHow many samples, and by whenSampling is 6-10 working daysA sample schedule nobody agreed
11. Bulk windowThe date the goods are neededWhether the 35-50 day window fitsA date that cannot be met
12. Destination and IncotermPort or door, and the ruleFreight, insurance and documentsA price on the wrong terms
13. Payment termsWhat the buyer can acceptT/T 30/70 is the standard positionA negotiation after the price
14. Inspection requirementLevel, standard, who paysAQL 2.5 under ISO 2859-1An inspection nobody booked
15. Response deadlineA date, and the name it goes toMakes the process move at allAn RFQ that sits unanswered

How Do You Write the Material Direction Without a Finished Pack?

Give a direction and an acceptable range rather than a single specification. "600D polyester, PU coated, or a comparable coated shell at a similar weight" tells the other side what class of material to cost and leaves room for a suggestion. "Polyester" tells them nothing and "600D" tells them one number out of four that matter.

Where a physical reference exists, say so and send it or name it, and mark which parts of it are the ones that must be matched rather than approximated.

Where the buyer has a physical reference, say so and send it or name it. A reference bag is worth more than a page of description, because it carries the hand, the weight and the construction at once. Where the reference is a competitor's product, mark which parts of it are the ones that matter.

What to write when the pack is not finished

  • The material class rather than a single specification, with the weight or thickness stated.
  • An acceptable second option, so the other side can suggest rather than guess.
  • A named physical reference if one exists, with the parts that matter marked.
  • The target price, so the direction can be costed against it.
  • A clear statement that the number is an indication until the pack is signed.

Why Does Quantity Need Splitting by Colourway?

Because one style is not one buy. A 500-piece order split across two colourways is two dye lots, two sets of trim, and possibly two material purchases that each clear a minimum. Price breaks are applied per style and colourway, not per order, and the RFQ has to say how the total splits.

This is also where MOQ is decided. At 500 pcs per style and colourway, an order of 500 split four ways does not meet the minimum in any of the four. Stating the split on the RFQ lets that be addressed at quotation rather than at order.

RFQ quantity table showing a total split across three colourways
Price breaks and dye lots are per colourway, not per order.

How Do Testing and Compliance Belong on an RFQ?

As a list of named standards and documents, because laboratory testing is a real cost and a real lead time. A buyer who asks for a restricted-substance statement is asking for a document that has to be produced and paid for; a buyer who asks for a colourfastness grade is asking for a test that has to be booked.

Name the market as well as the standard. REACH is a European Union position, Proposition 65 is a California position, CPSIA applies where the product is a children's product, and a GRS transaction certificate is what supports a recycled-content claim. Each has a different cost and a different document behind it.

Six compliance lines. The last two are the ones that surprise buyers because they are booked rather than written.
Market or claimWhat to name on the RFQWhat it costsLead time effect
European UnionREACH restricted-substance statementA document and, where testing is needed, a laboratory feeDays, if the report exists
CaliforniaProposition 65 positionA documented position on listed substancesDays
Children's product, USCPSIA testing and tracking labelThird-party testing on each materialAdds to the sampling window
Recycled contentGRS transaction certificate numberCertificate cost per shipmentAdds a document step at shipment
Colourfastness claimAATCC method number and gradeA laboratory test per shadeAdds days if it is not on file
Food contact, linerMigration testing on the actual linerA laboratory reportWeeks if the liner is new

What Should the Response Deadline and Format Ask For?

A date, a named recipient, and a format: a unit price at a stated quantity and Incoterm, a material list, a sampling schedule, a bulk window, and the assumptions the number rests on. That last item is the one that matters most and the one buyers never ask for.

Asking for the assumptions converts the quotation from a number into an argument. A price that says "based on a 600D shell, a stock black hardware set, and a 500-piece single-colourway buy" can be checked against the RFQ in five minutes. A price that says "USD 4.80" cannot be checked at all.

How Does Destination Change What the RFQ Must Say?

Destination sets the Incoterm, and the Incoterm sets what is in the price. FOB Xiamen puts the goods on the vessel and stops; CIF carries them to the destination port; DDP carries them to the door and includes the duty. Three quotations on three different rules are not comparable until they are put on one.

The RFQ should therefore ask for the Incoterm explicitly, with the named place written under the Incoterms 2020 rules — FOB Xiamen rather than FOB China — and should ask for the freight and duty layers to be shown separately where the rule includes them. The Incoterm decision tool walks through which rule fits which buyer.

Three quotations side by side on FOB, CIF and DDP terms
Three prices on three rules are not comparable until they are put on one.

What Does the Inspection Field Actually Commit?

A level, a standard, a sample plan and who pays. AQL 2.5 at General Inspection Level II under ISO 2859-1 is the standard position, and naming it on the RFQ means the inspection is booked as part of the programme rather than argued about at the end of it.

Where the buyer wants a level other than 2.5, the RFQ is the place to say so, because the level changes the sample size and therefore the cost of the inspection. A plan at 1.5 with a weak defect list is looser in practice than a plan at 2.5 with a real one, and the comparison is set out in the AQL 1.5 against 2.5 note.

What Happens After the Fifteen Fields Are Filled?

The RFQ goes out with the pack where there is one, and with the sketch where there is not. What comes back is a unit price at a stated quantity and Incoterm, a sampling schedule of 6-10 working days, a bulk window of 35-50 days from written sample approval, and a list of assumptions. Those four things together are a quotation.

The next step is to check the assumptions against the fifteen fields, line by line, and correct any that do not match. That check is the whole point of having filled the form in: it turns a price into something that can be argued with on paper rather than on the telephone.

What Does a Finished RFQ Cover on One Page?

Short, and shorter than most buyers expect. A quarter page of identity and commercial terms, a line per input, and the pack or the sketch attached. The document that takes two hours to write is usually the one that tried to describe the bag in prose instead of attaching the pack.

The test of a finished RFQ is whether somebody who has never met the buyer could price from it without asking a question. If the answer is yes, the fifteen fields are done. If the answer is no, whichever field they would have asked about is the one still missing.

How Should the RFQ Be Kept After the Quotation Arrives?

With the quotation, as one record. When the second run is quoted twelve months later, the original RFQ is the fastest way to work out what changed: a different quantity, a different material, a different Incoterm, or a different exchange rate. Without it, the comparison is done from memory and the memory is usually kind to the buyer.

A programme that keeps its RFQs also keeps its arguments. Where a price moves on a repeat, the RFQ says which input moved, and that is the difference between a negotiation and a dispute. The development calendar note explains why those inputs move the date as well as the price.

There is a version control point buried in this that is worth stating plainly. The RFQ that produced the accepted price is a document with a date on it, and so is the pack revision it was issued against. Twelve months later, when the second run is quoted, those two dates are what tell the buyer whether the two are being compared on equal terms.

Get the fifteen fields checked before you send

Send the RFQ as it stands. You get the missing fields marked and the assumptions the other side will have to make instead.

Frequently Asked Questions

How many fields should a bag RFQ have?

Fifteen: identity, description, quantity per colourway, target price, drawing status, material direction, hardware direction, artwork status, testing, sampling expectation, bulk window, destination and Incoterm, payment terms, inspection requirement and response deadline.

Should I put my target price on an RFQ?

Yes. It tells the other side which construction directions are worth costing, and it prevents a specification being costed that the buyer cannot sell at.

What if I do not have a tech pack yet?

Say so on the RFQ, send the sketch, give a material class with an acceptable second option, and state that the number is an indication until the pack is signed.

Why does quantity need to be split by colourway?

Because price breaks apply per style and colourway. An order of 500 split four ways does not meet the 500 pcs minimum in any of the four.

What Incoterm should I ask for?

Name the rule with its place: FOB Xiamen rather than FOB China. Ask for freight and duty to be shown separately where the rule includes them.

Do I need to name testing standards on an RFQ?

Yes, because laboratory testing is a cost and a lead time. Name the standard and the market the claim is made in.

What does a response deadline do?

It makes the process move, and it lets the buyer ask for a format: a unit price, a material list, a sampling schedule, a bulk window and the assumptions behind the number.

Why ask for the assumptions behind a quotation?

Because a price that states its assumptions can be checked against the RFQ in five minutes, and a bare number cannot be checked at all.

What is the standard sampling window?

6-10 working days from a signed-off pack, widening to 12-15 working days on a complex style with welded seams or multi-panel foam.

What is the standard bulk window?

35-50 days from written sample approval, inspected at AQL 2.5 under ISO 2859-1 at General Inspection Level II.

Should the RFQ state the payment terms?

Yes. T/T 30/70 is the standard position, and agreeing it on the RFQ avoids a negotiation after the price has been quoted.

Does the inspection level belong on the RFQ?

Yes, with the standard and who pays. The level changes the sample size and therefore the cost of the inspection.

What is the difference between a quotation and an indication?

A quotation rests on a signed pack and can be held to. An indication rests on a sketch or a description and moves when the pack is finished.

How long should a finished RFQ be?

Short. A quarter page of identity and commercial terms, one line per input, and the pack attached. Length usually means the bag is being described in prose instead of specified in a pack.

Should I keep the RFQ after the order is placed?

Yes, with the quotation. On a repeat it is the fastest way to see which input moved, and it turns a negotiation into a comparison.

People Also Ask

What should a bag RFQ include?

Fifteen fields covering identity, description, quantity per colourway, target price, drawing status, materials, hardware, artwork, testing, sampling, bulk window, Incoterm, payment, inspection and deadline.

How do I write an RFQ for custom bags?

As a form rather than a message, so every input the price depends on is present. Ask for a unit price, a material list, a schedule and the assumptions behind the number.

Do I need a tech pack to send an RFQ?

No, but without one you get an indication rather than a quotation. Send the sketch, give a material class and say the number is provisional.

Why does an RFQ ask for quantity per colourway?

Because price breaks and dye lots are per colourway. A total figure hides whether each colourway clears the minimum.

What is the standard Incoterm to ask for?

FOB Xiamen, written with its named place under the Incoterms 2020 rules. CIF and DDP are available and cost differently.

Sources and further reading

Every figure on this page is either our own programme data or attributed below. Open the originals before you write them into a specification.